RE:Wendell Filer Martin Roundabout Project
Request for Qualifications
The CivilScience tea m appreciates the o p po rtu n ity to su b m it th is proposal for the Wendell FilerMartin Roundabout Project.
Our team is excited about the opportunity to continue in providing quality design services to the City of Twin Falls.We are
experienced in and fully understand the requirements and details associated with the proposed project.The key personnel
identified in this submittal are fully committed to meet the quality and schedule expectations of the City of Twin Falls for
this project.We offer the following key advantages:
• Recent successful design,ROW,and construction engineering and inspection projects for the City of Twin Falls.
• The dedicated services of Jake Southwick having managed roadway design and construction projects in urban
settings like the recent Filer-Hankins Intersection and Falls-Eastland Intersection projects.
• Successful in evaluating and identifying cost-efficient design applications to maximize construction budget.
• Complete understanding of the Wendell Filer Martin Roundabout Project including needs,constraints and savings
opportunities.
• Extensive knowledge of Twin Falls Standards,design process,and construction standards specifications.
• Successful similar roadway widening design and construction projects within the City of Twin Falls.
• A dedicated team of engineers experienced with design and construction of roundabouts.
• Design and Construction experience/knowledge resulting in thorough and accurate plans and bid documents.
• Reputation for providing cost-effective designs with minimal change orders.
The Wendell Filer Martin Roundabout will be crucial to the success of potential future roundabouts within the City of
Twin Falls. Designing a useful and user-friendly roundabout will help educate the traveling public to the safety benefits of
using roundabouts.Our extensive past and current experience collaborating with the City of Twin Falls,Twin Falls Highway
District, and the Twin Falls Canal Company has uniquely positioned us to help the City complete this project successfully.
Our team's experience having designed and oversaw the construction of roundabouts is an added benefit to the City,the
cost,and schedule of this project.
Civil Science has assembled a design team primarily located out of our Twin Falls Office (376 Falls Ave) with an ideal
combination of project experience and technical expertise in each of the critical project disciplines.lake Southwick will be
the designated Project Managerfor this project and will proactively respond to project needs through timely communication
and comprehensive project administration. His contact information is as follows:
Main Contact
Civil Science Jake Southwick, PE Project Manager 208.995.4610
We pledge to provide cost-effective solutions using practical design applications,timely personal response,and superior
quality service.The Civil Science team looks forward to assisting the City of Twin Falls in providing another successful project.
Res/W.Southwick,
ectfull
J PE
Project Manager
OFF' i0
❑. _ www.civi[science.com
rkS,civilscience
PROJECT Jake's recent experience of successful design projects includes
the following:
We offer the City of Twin Falls the services of Jake Southwick, PE,as
the Project Managerforthe Wendell Filer Martin Roundabout Project. Filer-Hankins Intersection. Twin Falls, Idaho (Project Manager)—
Jake provides 16 years of experience working on local, state, and Jake successfully managed and provided design and construction
federal transportation related projects in Idaho and Utah and has engineering services to accommodate the increasing development
a proven ability to manage and deliver projects on time and within in this part of town.This project included widening the intersection
budget. He has managed a wide range of design and construction and extending the east leg of Filer for future development.Jake and
projects involving reconstruction and rehabilitation projects in both the Civil Science team worked with the City to provide the record of
urban and rural settings including roundabouts. Jake has forged survey and legal descriptions required to purchase the right-of-way
many partnerships with key partners needed for this project such as needed along Hankins to accommodate the new intersection. The
the Twin Falls Highway District,the Twin Falls Canal Company, Idaho design included extendingthewaterservices along Filerand Hankins
Power,and most importantly,the City of Twin Falls.This allows Jake for future development and revisions to the irrigation system within
to quickly resolve issues and to ensure project goals and objectives the project limits.The design also included installation of a storm
are met. He is an innovative manager with a strong team-oriented drainage system to accommodate the new intersection. Upon
approach to decision making and problem solving.With his diverse completion of the design and right-of-way services, lake provided
background and knowledge as an Engineering Manager over design/ management of the Construction of the project.lake worked closely
construction,Jake is uniquely qualified to manage this project and with the City and Contractor to resolve utility conflicts found in the
provides proven experience to successfully deliver this projectwhile field during construction.This project was completed on time and
resolving issues early through the design process. under budget.
JAKE SOUTHWICK,PE I CIVIL SCIENCE Eastland—Falls Intersection.Twin Falls, Idaho (Project Manager)—
TWIN FALLS,ID i PROJECT MANAGER Jake successfully managed and provided design and construction
M.E.&B.S.Civil Engineering,Utah State engineering services to address the reconstruction of the Eastland
University-Idaho PE#15991 —Falls Intersection using Portland cement concrete pavement.
Jake will provide the Project Management lake oversaw the reconstruction of this major City arterial and
services for this project from start to finish with truck corridor with the help of the Civil Science team to provide
100% involvement in the design, ROW, and along-lasting drivable intersection. The Portland cement concrete
11.1"1,i, ,hiw construction process. He is located in our Twin pavement was used to prevent future rutting that typically occurs
Falls Office and is the current Office Manager.He will be responsible at the intersections due to the start-stop motion of heavy truck
for the quality and timeliness of the work and for ensuring that traffic. Working closely with the City Staff and Contractor, Jake was
personnel and needed resources for the project are available.Jake is able to provide a plan that allowed the work to be completed in
familiar with the needs of this project and was specifically selected minimal time. This resulted in a shorter impact to the traveling
as the Project Manager based upon the following: public. Upon completion of this project,Jake and the City received
several praises for the quick project completion. Jake also worked
to provide improved storm drain and future use conduit.This was a
4 Experience managing transportation design and successful project that was carried out from design to construction
construction projects for the City of Twin Falls. under budget and ahead of schedule.
H
4 Local design staff availability,in addition to design staff Eastland Drive North and Pole Line Road:Bitterroot Dr to Mountain
resources from other office located in Utah and Nevada View Dr.Twin Falls,Idaho(Project Engineer)—Jake provided the design
where roundabouts are commonly used. and construction inspection for this 1-mile pavement widening and
rehabilitation project.This project, utilizing the ISPWC specifications
4 Complete understanding of project needs,constraints, and City of Twin Falls Supplemental Specifications, repaired and
and opportunities through conversations with City Staff. restored this major City arterial and truck corridorfor improved traffic
flows.Jake assisted in fast-tracking the design process to advance the
4 Successful design and construction services for the bidding schedule to occur when contractors were developing their
City of Twin Falls including full depth reconstruction, work schedules for the upcoming construction season. Civil Science
intersection improvement design,parks projects, also advised the City to widen the roadway in certain areas to address
pathways,and ROW negotiations. existing congestion issues.In coordination with the City,Jake assisted
in developing a plan and approach to widen the roadway without
4 Extensive knowledge of City of Twin Falls design process having to purchase any additional property.
with 14+years working on projects within or near the City.
Additional projects include: Golf Course Rd Phase 3 & 4 1 Harmon
4 A personal commitment to project delivery,innovative Park Parking Lot, Twin Falls 1200 N; US-93 to 550 E Jerome 1300
engineering solutions,public and contractor safety,and W;100 N to 300 N Jerome I Golden Valley Road:1500 W to 900 W
a focus on mobility and excellence. 45th West:65th S to US-20 I Annis Highway:Rigby to Menan-Lorenzo
Highway I Yale Road Phases 3,3a,and 4 11200 West Phase 1 &2.
REQUEST FOR QUALIFICATIONS CITY OF
TWIN FALLS
WENDELL FILER MARTIN ROUNDABOUT PROJECT
civilScience
FIRM AND STAFF Having our office located within 1.5 miles of the project,our staff offers
distinct advantages to this project that include cost savings,and quick
Civil Science is a full-service civil engineering firm built upon the responses.With our proven experience working on City of Twin Falls
foundation of more than 40 years of continuous experience in projects, we are familiar with the current issues the City is engaged
providing innovative engineering solutions that directly benefit the in and have in-depth knowledge of City standards and practices.
City of Twin Falls.We offer the availability of over 100 staff including From our Twin Falls office,we can provide survey and CAD resources,
professional engineers, land surveyors, CAD designers, field construction technicians, construction managers and professional
technicians, and other support personnel located in Utah, Nevada, staff to meet the City's engineering needs within minutes. This
North Dakota,and Ohio.Their engineering experience isstrengthened allows the Twin Falls engineering projects to be fully developed in
with continual education, certification, and training opportunities our Twin Falls office.As a self-sustaining local office,we can provide
providing expertise to address the Twin Falls engineering needs.Our superior services faster and more economically. We also have the
staff is fluent in the latest versions of AutoCAD Civil 3D, AutoTURN, experience and understanding of local agency codes,regulations,and
and OpenRoads Designer.They are also well versed in the ISPWC and specifications to reduce changes/revisions as the project progresses.
the City of Twin Falls Revisions to the ISPWC,the AASHTO Policy on
Geometric Design,AASHTO Roadside Design Guide,AASHTO Roadway Qualifications for key personnel and their involvement with this
Lighting Guide,AASHTO Bicycle Facility Design Guide and the Manual project are as follows:
on Uniform Traffic Control Devices. Having design and construction
experience in Twin Falls, our staff is experienced and can identify ROB RAMSEY,PE I CIVIL SCIENCE
constructability issues during the design process. In addition to TWIN FALLS,ID I QA/QC MANAGER
our engineering expertise, we are well versed in performing public (10%Involvement during the design process)
outreach for projects similar in nature.This experience includes the B.S.Civil Engineering,Brigham Young University-
US-30 Blue Lakes to Eastland project and the completed Eastland- Idaho PE#9454
Falls Intersection project. Rob has 29 years' experience providing transportation planning,
Civil Science also works closely with Harmony Public design, and construction management for state and local projects,
••• 18 of those years being at Civil Science. Before Civil Science, Rob
*� Involvement who has years of experience performing was a Resident/Regional Engineer for ITD D4 overseeing the design
public outreacchh throughout Idaho and Utah. and construction of State and Federal Transportation Projects.
In this position he acted as project manager and construction
CITY OF lISIGN �� administrator for contracts including multiple road realignment and
`WIN FALLS intersection improvement projects to provide safer roadways. He
LEAD DESIGN has provided technical support,design,and contract administration
BENBINGHAM,PE�i] for projects including bridges, roadway widening, storm sewer,
irrigation,and reconstruction using a variety of ballast sections and
L ROUNDABOUT DESIGN ENGINEER designs. Rob's strong construction and design background results
F Q��a JUSTINJONES,PEau]] in proficient QC/QA skills. His expertise will be used to ensure the
SERVING needs and requirements of this project are completed and met
SURVEYOR through thorough reviews. Projects include: 3500 E Rock Creek
MITCH BARRERAS,PES[if] Crossing 13000 East& Foothill Rd Curve I Golden Valley Road:1500
SURVEY CREW CHIEF W to 900 W 145th West: 65th S to US-20 I Annis Highway: Rigby to
.* A-- Menan-Lorenzo Highway I Yale Road Phases 3,3a,and 4 11200 West
J JAKE SMITH,CSi3[Ti] Phase 1 &2 I Eastland:Orchard Dr to Kimberly Road I Eastland/Pole
DRAINAGE I Line: Bitterroot Drive to Mountain View Drive.'
f�
LUKE POLITIS,PE ist�
BENJAMIN BINGHAM,PE I CIVIL SCIENCE
-- TWIN FALLS,ID I LEAD DESIGN ENGINEER
(80%Involvement during the design,ROW,
PROJECT MANAGER and construction processes)
;�' CONSTRUCTION B.S.Civil Engineering,Brigham Young University Idaho
- Idaho PE#19331
Benjamin is a Professional Engineer who began working for Civil
ANDY iAHRN,PE[Te Science in April of 2015 as an intern.He now has 9 years of experience
' I ; providing transportation engineering support and design including
MicroStation, InRoads SS4, OpenRoads, as well as AutoCAD Civil
JORDAN BROWNING,EI[in 3D. Ben is known by many for his attention to detail and quality of
OA/OC MANAGER work. His transportation design experience includes realignment/
UI I IVL LU UHIIUIY AY
reconstruction, widening, pavement rehabilitation, roundabout
Lehi,Utah..............................[LU] rwm falls,Idaho.................... design, and intersection improvements including modeling. His
Salt lake City,Utah...............[SI.] experience includes designing a 4-legged roundabout as an
REQUEST FOR QUALIFICATIONS CITY OF
TWIN FALLS
WENDELL FILER MARTIN ROUNDABOUT PROJECT
rkS,civilscience
intersection improvement alternative. Ben's experience in design Cobalt Project Boundary Survey I ING Deep Creek Boundary Survey
and construction has taught him to identify problems to be resolved AGPROfessional Aerial stockpile volume monitoring.
during the design process leading to cleaner, more cost-effective
plan sets. Ben will act as the Lead Designer for this project. As a JAKE SMITH,CST 3 I CIVIL SCIENCE
licensed Professional Engineer, he will ensure the plans meet the TWIN FALLS,ID -SURVEY CREW CHIEF
standards set by the City of Twin Falls and the ISPWC. Ben's recent (100%Involvement during design survey
design Projects include:Eastland—Falls Intersection I Eastland Drive and ROW processes)
North and Pole Line Road I Eastland Drive South—Orchard Dr to Acquiring B.S., Idaho State University-Anticipated
Kimberly Rd I Golden Valley Road I I-94 Business Loop. Completion:2026
Jake provides 20 years of in-depth field and office experience
JUSTIN JONES,PE I CIVIL SCIENCE in a variety of different aspects of land surveying including
F LEHI,UT ROUNDABOUT DESIGN ENGINEER transportation surveying. This includes control surveys, boundary
(50% Involvement during the design process) surveys,topographic surveys,right-of-way surveys,dam monitoring,
B.S.Civil Engineering,Utah State University—Utah PE monument perpetuations,ALTA surveys, bathymetric surveys, Flood
#353820-2202 Certification,and other related activities.Jake along with the rest of
Justin is a Civil Engineer that has worked in the development and our survey crews utilize Trimble GPS equipment(R12i head with TCS7
infrastructure field for more than 25 years. Justin has extensive data collector)for RTK and Static Opus control surveys with GLONASS
experience in both construction and design, having designed, capabilities.He is well versed and experienced in using SX-12 Trimble
managed,and inspected a variety of roundabout projects in Nevada, Scanner to survey up to 1,000 feet at 50,000 points per second while
Utah,and North Dakota.Justin's design experience includes grading, providing a 360-degree laser scan with plus or minus 2-millimeter
stormwater design/analysis,utilities,vertical and horizontal roadway resolution from its setup location. In addition to this equipment,
design, signage & striping, and sedimentation/erosion control. His Jake is well versed in AutoCAD Civil 3D,Trimble Business Center,and
construction management experience includes structure and utility Deed Plotter. Some of Jake's recent Twin Falls Projects include: TF
rehabilitation work at Dinosaur National Monument in eastern Utah Gun Club Pathway I Harmon Park I Wendell Street Sidewalk I Filer-
and Bryce Canyon National Park in southern Utah. Justin has also Hankins Intersection I Downtown Revitalization I Rock Creek Sewer
performed various engi neeri ng tasks on transportation and municipal Grandview and Harrison Sidewalks I Canyon Springs Grade.
projects in North Dakota, Nevada,and Utah, in addition to providing
quality control reviews of improvement plans and specifications for ANDY ZAHRN,PE I CIVIL SCIENCE
various projects.Projects include:1200 East Corridor Roundabouts I TWIN FALLS,ID I LEAD INSPECTOR
400 North 300 West Roundabout 1 500 East 11100 South Roundabout (50% Involvement during construction
1 Mill Road11100 South Roundabout 1 400 North/SR-51 Roundabout. inspection process)
B.S.Civil and Environmental Engineering,Utah State
MITCH BARRERAS,PLS I CIVIL SCIENCE University- Idaho PE#17992
TWIN FALLS,ID SURVEYOR Andy offers significant construction inspection and field engineer
(15%Involvement during design survey inspection for major reconstruction projects with over 10 years
and ROW processes) experience. Andy's transportation construction experience consists
I—J T A.A.S.Civil Engineering Technology, Idaho State of oversight, inspections, material testing and acceptance, and
University-Idaho PLS#LS-13024 documentation services on these projects.Andy is well versed with
Mitch offers over 31 years of in-depth experience in many distinct the ISPWC Standards having worked on projects such as the Eastland-
aspects of[and surveying including both boundary and transportation Pole Line project. Andy uses his experience to coordinate with
surveying.He recently joined Civil Science in 2020 after managing the contractors and testers to ensure the proper procedures and tests
surveying program for Bayer's Phosphate Mines(previouslyMonsanto) are provided to create a long-lasting quality product.He has proven
in Soda Springs, Idaho. While working for Bayer, he implemented a track record of his attention to detail,follow-through,and a personal
UAS surveying program and methodologies which allowed him to commitment to every project he is assigned to.Some ofAndy's recent
manage the surveying for multiple sites in remote locations. He has inspection/documentation Projects include:I-84 Burley IC I Eastland
worked closely with private parties and local governments to provide Drive North and Pole Line Road I S 2nd West St Bridge I Ora Road
quality surveying products and to facilitate cooperation between Bridge I I-15 Northgate IC I Old Hwy 37 The Narrows I Heyburn 21st
multiple parties on boundary surveys and various design projects. Street I Cheney Drive I Bob Barton Road I S Canal Bridge.
Mitch has also previously worked for a national road and bridge
contractor and is deeply knowledgeable and experienced with survey JORDAN BROWNING,El CIVIL SCIENCE
services associated with transportation design and construction. TWIN FALLS,ID INSPECTOR
This includes control surveys, location surveys,topographic surveys, (100%Involvement during construction
right-of-way surveys,right-of-way plans including deed descriptions, inspection process)
construction staking, UAV Drone Survey, Lidar and High-Definition B.S.Civil Engineering,Utah State University-EIT
Survey, and related survey activities. Projects include: 1st Street, Jordan began his Engineering Experience working for UDOT in 2018
Ammon ID I Kimberly Interchange 1 100 S and US-93 in Jerome Co. as an intern performing inspection on multiple projects throughout
I Timberlake Apartments ALTA I Crockett Subdivision I El Milagro Lot the summer gaining experience in project management tasks.
Split I US Highway 93100 South Construction Survey I Jervois Salmon Jordan's experience since than includes survey and design projects
REQUEST FOR QUALIFICATIONS CITY OF
TWIN FALLS
WENDELL FILER MARTIN ROUNDABOUT PROJECT
civilScience
for the City of Twin Falls and ITD related engineering. Jordan's innovative engineering solutions providing project cost savings. To
experience includes roadway modeling, plan sheet development, illustrate our active participation within Twin Falls,we have included
and surveying to name a few. Jordan has become proficient in his information on some recent City of Twin Falls transportation/traffic
modeling skills within MicroStation InRoads SS4, OpenRoads, and projects. We have also included some additional representative
AutoCAD Civil 3D to provide detailed design and CADD assistance projects that detail our transportation and traffic engineering and
on multiple projects. Jordan has also been the Lead Inspector on design capabilities and construction management experience.
several construction engineering and inspection(CE&I)projects.For
this projectJordan will assist in the construction inspection.Projects
include:I-84 Heyburn IC I Filer-Hankins Intersection I Harmon Park
Parking Lot Golf Course Road I Little Wood River Bridge I Deep -
Creek Bridge N 500 West I SH-81 Declo to Burley 13000 E Foothill
Rd I Golden Valley Road I I-15 Northgate IC I Ora Bridge I S 2nd W St ._.
Bridge I N Salem Road.
LUKE POLITIS,PE I CIVIL SCIENCE
SALT LAKE CITY,UT I DRAINAGE
(10%Involvement during the design process)
B.S.Civil Engineering,University of Utah,Utah PE _ V
' #11240768-2202 -
Luke brings 9 years of experience in all aspects of drainage analysis
to support transportation projects requiring storm drain, erosion Filer-Hankins Intersection
protection, and water quality design. He recently completed To accommodate the increasing development in this part of town,
drainage design for the similar US-40; Passing Lanes and Region the City of Twin Falls hired Civil Science to design the construction
4 Culvert Rehabilitation projects where his team designed storm of Filer Avenue east of Hankins Road(a major collector).This project
water collection/conveyance systems at ephemeral washes using consisted of designing the reconstruction of the east half of Hankins
culverts, drainage structures, and drainage swales with roadbed Road through the intersection to the most recent City of Twin Falls
armoring.Forthis project,Luke will assist with the hydraulic analysis, standards and designing the construction of the east leg of Filer
drainage study, any stream alteration permit that may be required Avenue for approximately 300'to the most recent City of Twin Falls
to pipe and/or relocate the existing irrigation facilities.Luke's recent standards. Civil Science provided CADD design services in AutoCAD
Projects include: Bangerter Three Interchanges Design-Build I Coal Civil3D to develop the construction drawings and a subgrade surface
Creek Road Widening Phase II 1 US-89 Progressive Design-Build I model for the contractor to use during construction. The project
Bangerter Four Interchanges Design-Build. included utilities such as water,storm drain,and pressure irrigation,
curb and gutter,sidewalk,stormwater retention basin,and roadway
EXPERIENCERELEVANT PROJECT typical sections. Civil Science assisted in the inspection of Portland
cement concrete pavement, curb and gutter, concrete sidewalk,
AND REFERENCES ADA ramps and painted pavement markings. Civil Science also
provided construction engineering and inspection services during
Our mission at Civil Science is to provide civil engineering services the construction of the project.This included reviewing submittals,
that exceed our clients' expectations for quality, schedule, and overseeing materials testing, preparing weekly coordination
budget adherence. With an office in Twin Falls, it is critical to meeting agendas and leading out the meetings, and ensuring that
provide the best service to our community and tax payers. Civil the project was constructed according to local specifications.
Science offer a proven track record and an extensive background in
providing engineering services on a wide variety of transportation/ Location:Twin Falls, ID
traffic projects. We offer a wide range of specialized transportation Budget:Design &CEI $97K Const:$648K
and traffic engineering services including roadway and traffic Year:2021
control design, innovative intersection enhancement design, Key Personnel: Jake Southwick (PM) I Jordan Browning I Mitch
roundabout design,signal design, ITS system design,traffic studies, Barreras I Jake Smith
transportation master planning, right-of-way services, hydraulic Reference:Erin Steele, PE,City of Twin Falls 1208.736.2275
design, planning, environmental evaluation and documentation,
utility coordination and design services, constructability review, Wendell Street Sidewalk
construction engineering management, and surveying among The City of Twin Falls hired Civil Science to complete the design
others. Our wide range of skills and abilities are integrated with of this sidewalk project on Wendell Street. Civil Science reviewed
one-on-one communication to facilitate an efficient, consistent the existing right-of-way between Robbins St and Falls Ave. and
design,especially important for the small to medium sized projects determined where new sidewalk,curb and gutter could be installed
often encountered in City roadway needs. Our background in on the East side to provide a safe route to school for children and
this area offers quantifiable benefits to the City of Twin Falls in pedestrians along Wendell St. Upon completion of the design,
the delivery of cost-effective services that enhance the value of the City worked through the deferral process with the residents
limited public funds. These benefits include solid plan sets using before putting the project out to bid. This allowed Civil Science
REQUEST FOR QUALIFICATIONS CITY OF
TWIN FALLS
WENDELL FILER MARTIN ROUNDABOUT PROJECT
11 civilsCience
to revise the plans as needed prior to
bid. This project was constructed while ► t �':
using a single lane closure. During
the construction process additional _
funds became available allowing the
project to replace the roadway section
all the way from the new sidewalk to -
the centerline of the roadway. This
project was completed on time and
under budget.
Location:Twin Falls, ID Harmon Park Parking Lot
Budget:Design &CEI $34K Const:$298K Civil Science successfully provided design and construction
Year:2021 engineering services for the reconstruction of the existing Harmon Park
Key Personnel: Jake Southwick (PM) ' Jordan Browning I Mitch Parking lot.Civil Science worked with City Officials to prepare a design
Barreras I Jake Smith that not only boosted aesthetic appeal with landscaped curb islands
Reference:Erin Steele, PE,City of Twin Falls 1208.736.22755 and rubbed-finish retaining wall,but also improved site drainage and
maximized parking.Civil Science also provided CE&I services to ensure
the project met plan specifications and City standards.
Location:Twin Falls, ID
Budget:Design &CEI:$95K Const:$950K
Year:2021
Key Personnel:Jake Southwick(PM) I Jordan Browning I Jake Smith
' Reference:Josh Baird, PE,City of Twin Falls 208.736.2275
Eastland-Falls Intersection
Civil Science successfully provided design and construction
engineering services to address the reconstruction of the Eastland 1�
-Falls Intersection.This project included Portland cement concrete
pavement, storm drain, conduit, sidewalk, curb and gutter. Civil 1200 East Corridor Roundabouts.Logan,Utah
Science coordinated with the Contractor and the City to permit a Civil Science designed a unique shaped roundabout for the offset
full closure of the intersection to complete this work. This full 1000 North intersection with 1200 East which prioritized north/
closure allowed the work to be completed within half of the original south traffic on 1200 East.The project also included the design of a
anticipated schedule.This reduced the duration of the impact to the standard roundabout at 800 North and 1200 East which minimized
traveling public by almost weeks.Upon completion of the workthe impacts to the existing Utah State University(USU) IT Building, USU
City and the Contractor received many accolades of appreciation for tennis courts and Logan City Cemetery while maintaining access
completing the project in such a short time frame.This accelerated for large truck traffic. The design included the reconstruction of
schedule assisted in reducing the administrative costs associated 1200 East corridor between 700 North and 1000 North including
with construction for all parties.The full closure also provided the shared lane bicycle facilities, connection to existing bicycle lanes,
opportunity to construct a more consistent, longer-lasting product. bicycle on/off ramps at roundabouts, replacement of existing city
As a result of these innovative design and construction methods, water mains, installation of new USU water mains,and installation
the project was successfully completed well within the schedule of a new city storm drain system. CS provided full Construction
and under budget while providing the needed reconstruction of this Management services for the project with full-time inspections and
heavily traveled corridor. management. CS worked with Logan City and Utah State University
Facilities throughout design and construction.
Location:Twin Falls, ID
Budget:Design &CEI:$211K Const:$950K Location:Logan,UT
Year:2019 Budget:Design:$500K Const:$7.3M
Key Personnel:Jake Southwick(PM) I Rob Ramsey I Andy Zahrn Year:2024
Reference:Josh Baird, PE,City of Twin Falls 1208.736.2275 Key Personnel:Justin Jones
Reference:Alex Oliphant,City of Logan 1435.716.9165
REQUEST FOR QUALIFICATIONS CITY OF
WENDELL FILER MARTIN ROUNDABOUT PROJECT TWIN FALLS Page 5
civilScience
..4
GEOGRAPHIC CONSIDERATIONS
The Civil Science office in Twin Falls is strategically positioned for
' our delivery of prompt and efficient engineering services to the
City of Twin Falls. Located at 376 Falls Avenue, we are centrally
located and less than 5 minutes from the City of Twin Falls Offices.
Since we are actively and intimately involved with the City of Twin
' Falls, and coupled with our local roots, we take ownership in the
engineering product we provide to the City. We clearly understand
that the product will have an immediate impact to our families and
/ our overall community.As a local business we are committed tothe
Mill Road/1100 South Roundabout,Spanish Fork,Utah development of this community.These efforts were demonstrated
Civil Science designed a 34eg roundabout with a future 4th leg by our work on Filer-Hankins, Eastland Drive, Blue Lakes Boulevard,
adjacent to American Leadership Academy charter school to Cheney Drive, Washington Street/Falls Avenue Signals, Shoshone
alleviate traffic congestion due to student drop-off and pick-up. Street Signs and Turn Bay,and the Intersection Washington Street/
The design included a right turn bypass lane to further mitigate Caswell projects,to name a few. Having worked for the City of Twin
congestion, sewer and water stubs for future development and Falls forthe past18 years,we have an excellent relationship with the
coordination with Spanish Fork Light & Power to design lighting City Department Supervisors and enjoy collaborating to address the
and communication for the project. CS designed full roundabout City's needs. This includes coordination with the City Engineering,
signage and striping including rectangular rapid flashing beacons Streets,Water,and Sewer Departments,as well as the Urban Renewal
(RRFB's) for the east crosswalk which serves as a safe walking Agency, and the Planning and Zoning Department. By consistently
route for the charter school. CS worked with a landscape architect working with the City of Twin Falls, we are fully conversant in the
subconsultant to provide a unique center island design featuring a application of the City codes, regulations,standards,specifications,
statue representing the adjacent school's mascot. bid documents, practices,and policies.
Location:Spanish Fork,UT Civil Science has extensive experience working not only with the
Budget:Design:$100K Const:$800K City of Twin Falls, but also with other local groups, governmental
Year:2021 agencies and local utility companies,including:
Key Personnel:Justin Jones
Reference: Byron Haslam, PE,City of Spanish Fork 801.804.4543 •Greater Twin Falls Transportation Committee
•Highway Districts:Filer,Buhl,Jerome,Burley,Wendell,&Twin Falls
500 East/1100 South Roundabout.American Fork,Utah -Cities:Jerome, Rupert, Heyburn, & Burley
CS is currently completing -Counties:Twin Falls,Jerome, &Cassia
m m C� the design of a 3-legturbo
0 •State Government:ITD, DEQ, LHTAC, & Fish and Game
J ® roundabout with a future
4th leg. The intersection -Federal Government:USDA and FHWA
is located just east of -Utilities:PMT, Lumen,Idaho Power, Intermountain Gas,Sparklight,
an existing at-grade rail Fatbeam,TDS Telecom &Twin Falls Canal Company
crossing at 1100 South. -Other: Eastern Idaho Railroad
The initial intersection
p� concept included a traffic At Civil Science we understand the design requirements and
/• signal option, which process as defined in the ISPWC and City Standards. Being locally
was reviewed and due based we are prepared to meet with utilities such as Idaho Power,
to proximity to the rail TDS, PMT, Lumen, Intermountain Gas and City Council among
crossing, was replaced with the roundabout. Nearby distribution others, if requested/needed,to complete the public outreach and
facilities generate substantial delivery truck and semi-truck traffic. coordination necessary for a successful project. Upon approval of
To mitigate the potential traffic backup,a second lane was added to the agreed upon scope and estimate, Civil Science will coordinate
the roundabout for eastbound to northbound traffic movements, with the designated City of Twin Falls Project Managerto determine
which should minimize vehicle queueing across the rail. CS the proposed alternatives for consideration. The design process
coordinated with adjacent owners,which included new projects,to will proceed following summarized schedule shown on Page 7:
ensure designs matched.The design included upgrades to the city's
water and sewer system and a new storm drain system. Document submittals including Preliminary Design reviews, Final
Design Plans, Specifications, and Estimates will be submitted via
Location:American Fork, UT email to the appropriate City Project Manager for review. Through
Budget:Design:$148K the entire design process, Civil Science will coordinate with the
Year:2024 City Project Manager concerning the project progress and decision-
Key Personnel:Justin Jones making activities.
Reference:Rebecca Andrus,PE,City of American Fork 1801.763.3000
REQUEST FOR QUALIFICATIONS CITY OF
TWIN FALLSWENDELL FILER MARTIN ROUNDABOUT PROJECT
civilScience
APRIL MAY JUNE JULY AUGUST I SEPTEMBER I OCTOBER I NOVEMBER I DECEMBER
CONCEPT PHASE MMLMM�
PRELIMINARY DESIGN PHASE . M
6/9/2025-8/15/2025 .
FINAL DESIGN
ROW PHASE EMMI
BIDDING PHASE I
Upon approval of the final design plans lake and the Civil Science by the Contractor. This will warrant the design life of the roadway
team will assistthe City in the bid process.if funding for construction can be achieved. Upon any changes or problems identified in the
is not available upon completion of the design,Civil Science will work field during construction that were not previously identified during
closely with the City to find additional funding mechanisms such as design, the City's project manager will be notified. lake as project
grants.Once the project has been funded and bid, Civil Science will manager will confirm the City's project manager is informed of and
then proceed toassistwiththeConstruction Engineering&Inspection. agrees to any changes required prior to proceeding with the work.
Our vast construction experience with this type of work will allow Upon completion of the project Civil Science will perform a final
us to manage this project efficiently and effectively. Coordination walk-thru with the City and Contractor.This walk-thru will allow the
with the Contractor and Utilities will begin immediately to confirm City to review and approve the final product for acceptance prior to
any additional permitting and coordination required to perform releasing the Contractor from the Contract.
the work as identified during the design process is completed in a
timely manner thus preventing any delay to the project construction. Civil Science looks forward to the opportunity to assist the City of
With a staff of qualified WAQTC trained engineers, Civil Science will Twin Falls with this critical roundabout project that will determine
oversee and ensure the standards and testing requirements are met the consideration of future roundabout projects within the City.
ipCITY OF TWIN FALLS ��.
TWIN FALLS ORCHALARA SUBD
TAX#3284 IN LOT 9
N
AVE YJ �•
R405 ST ` Z ! + 8
,y��
♦� L t a�_�_ �-r J
+ �— —J y^— 804 FILER AVE W
_ � 1
28' R133 1
— — -r = 1 1 FILER AVE(30 MPH) �~
R!q R102 J L_� - - - - _ — — I1--+L •_ I1
R253 R43 20 MPH ^- - �`'`?�' M1
T
MARTIN STREET
DEVELOPMENT LLC p _
15'— PNIN FALLS - ��A'A l
+ R47 ORCHALARA SUBD I
• R83 \ '
\ + TAX#42821N LOT 4
Y�F \ 20 MPH - \ I
\ 20 MPH I d+ a y, I z 1
1 R77 .'•. 2.2 ACRES _V_ —o_ _ !
IONI-WAY
/ R125 1
/ +
END OF PROJECT
III III R97 \ 1
III III 1
Exhibit of conceptual roundabout provided by the City of Twin Falls -
REQUEST FOR QUALIFICATIONS CITY OF
TWIN FALLS
WENDELL FILER MARTIN ROUNDABOUT PROJECT