Loading...
HomeMy WebLinkAboutTWINID_0898GA_08 TRENCHING BORING RIGHT-OF-WAY PERMIT-compressed City Ot TWINID_0898GA_08 —AME No �o oQ� mwbdm PO Box 1907 203 Main Avenue East Twin Falls,ID 83301-1907 Phone(208)735-7265 CITY OF TWIN FALLS RIGHT-OF-WAY PERMIT FOR: TRENCHING / BORING PERMIT HOLDER(UTILITY COMPANY): TDS Metrocom, LLC UTILITY COMPANY CONTACT PERSON: Todd Naylor PHONE: (541)797-0539 CONTRACTOR: Tilson Technology Management PHONE: CONTRACTOR CONTACT PERSON: Barby Garcia CELL PHONE: (786)334-4227 LOCATION OF WORK: Candleridge Dr TYPE OF WORK: TRENCHING BORING X OTHER DESCRIPTION OF WORK: Directional Bore of both 1" and 1.25" HDPE Conduit & AXS 400 & 500 HH SKETCH SHOWING AREA OF WORK: On Permit See Attachment X As the applicant, I understand the conditions of the permit and will comply with the requirements set forth therein. Non-compliance to these conditions may affect approval of future right-of-way permits. Signature: Sa&,�aAa, Lyau-z�,- Date: 2/22/23 $50.00 PERMIT FEE: Collected by: Date: This permit is for the use of the City right-of-way only.No survey has been conducted by the City to determine the location of the right-of-way in this permit.Verification of right-of-way is the responsibility of the applicant. This permit does not alter franchise agreements. This permit is valid for 90 days from the approval date. Street Classification: Residential Collector/Arterial Alley Engineering Dept.Approval Date Engineering Dept. Final Sign Off Date • Please contact Garry Denton at 308-7255 or at gdenton(a,tfid.org for final sign off to close out this permit. • See page 2 for construction, inspection & testing requirements. Revised August 2020 Construction Requirements: • Applicant must contact DIGLINE at 1-800-342-1585,811,or through the WebTicket Program via their website at www.dialine.com.Underground utilities must be located and marked prior to any trenching or boring work. • All construction must meet the 2015 Idaho Standards for Public Works Construction (ISPWC) and the City of Twin Falls Revisions to the 2015 ISPWC (City Revisions). City Revisions including standard drawings can be found on the City website atwww.tfid.org. • All construction materials must be from a source approved by the City of Twin Falls Engineering Department (gravel, concrete, asphalt, etc.) These requirements include the asphalt patch-back in the street to the adjoining curb and gutter. • Applicant is responsible for site safety during construction activities including traffic control. • Applicant must provide a traffic control plan, which must be approved by the City, if there are to be lane or roadway closures. • The applicant must give the City 24 hours notice before any lane or roadway closures are permitted. Please contact Mark Thomson at 208-308-7326 with closure information. • Applicant must provide a map of the area the work will be taking place. Inspections & Testing Requirements: The following items shall be performed by an independent firm. The independent firm shall follow the required inspection & testing processes listed below and submit all inspection & testing documents to the City Engineering Department. Residential/Collector/Arterial Street Requirements: 1. A visual inspection is required on all subgrade dirt work. 2. Inspection & testing required on gravel base & concrete forms. 3. Inspection & testing required on gravel base for street section. 4. Submit all testing & inspection documents to the City Engineering Department. 5. Visual inspection with final sign off by City Engineering Department. Please contact Garry Denton at 208-308-7255 for final inspection and sign off. Allev Requirements: 1. A visual inspection is required on all subgrade dirt work. 2. Inspection & testing required on gravel base for alley section. 3. Submit all testing & inspection documents to the City Engineering Department. 4. Visual inspection with final sign off by City Engineering Department. Please contact Garry Denton at 208-308-7255 for final inspection and sign off. Revised February 2022