HomeMy WebLinkAboutRE: 448 Addison Ave - Following up with last appointment. Would like to know the next steps that need to be taken. He has included a drawing. Procedures. (6)
Rich Hall
From:Jon Victor
Sent:Friday, June 21, 2024 7:01 AM
To:'Behnam Ramezani'
Cc:Will Klaver
Subject:RE: 448 Addison Ave - Following up with last appointment. Would like to know the
next steps that need to be taken. He has included a drawing. Procedures.
Follow Up Flag:Follow up
Flag Status:Completed
Hi Ben,
To answer your question from yesterday, normally the foundation comes first so that you know where you need to
run the sewer to. You may want to plan ahead with your foundation contractor to make sure that they provide a
sleeve to go through the footing or foundation or whether they will dig below the footing. I am not sure where the
sewer line is located, but Will told me yesterday that he would reach out to you with that information.
Respectfully,
Jon Victor
Building & Mechanical Plans Examiner
208-735-7291
nd
City Hall (2 floor)
203 Main Ave. E.
Twin Falls, ID 83301
Revision/Change Orders send to
bsdpermits@tfid.org
Online permit PORTAL
From: Behnam Ramezani <porseshgar@gmail.com>
Sent: Thursday, June 20, 2024 5:27 PM
To: Kelly Wright <kwright@tfid.org>
Cc: Jon Victor <JVictor@tfid.org>; Jarrod Bordi <jbordi@tfid.org>; Jonathan Spendlove <JSpendlove@tfid.org>; Will
Klaver <wklaver@tfid.org>
Subject: Re: 448 Addison Ave - Following up with last appointment. Would like to know the next steps that need to be
taken. He has included a drawing. Procedures.
\[EXTERNAL SENDER\]
Good evening
To whom it may concern
1
Would you please help me with making the address 448 Addison Ave.
a valid address so the post office delivers to this address?
Sincerely, Behn
You can apply for an address through your local government
office. The process varies depending on whether the land is
within city limits or outside them.
Inside city limits: Contact the city government (building and
zoning department, geographic information systems
department, etc.) to assign an official address.
Outside city limits: Similar departments within the county
recorder’s or assessor’s office handle address assignments.
Having an address is essential for utility services, directing
visitors, and emergency response.
On Thu, Jun 20, 2024 at 12:17 PM Behnam Ramezani <porseshgar@gmail.com> wrote:
Good Afternoon
Hope you've all had a great summer so far
2
I am gathering data to build a foundation on the land at 448 Addison
Ave.
Should the sewer line come first or foundation comes first?
Is the city sewer line on Addison St or on the alley?
Please let me know
Sincerely, Behn
3
Key Points from Chapter 18 of the IBC Code 2018
4
5
6
On Tue, Jun 11, 2024 at 1:44 PM Behnam Ramezani <porseshgar@gmail.com> wrote:
Good Afternoon
Hope you've had a great day so far
7
The landowner has accepted my offer. The offer is contingent upon
obtaining the variance from the City of Twin Falls to build a
building and approval of the bid for the building.
There is a phrase in the agreement that says "The buyer chooses to
conduct inspections". In regard to the inspection step, in
8
association with the city records, do you see any legal problem or
restriction or potentially costly obligation other than the setbacks
that you discussed with me in our valuable meetings so far?
Based on my amateur in-person measurements on the property and
the setback criteria I got from the City, if I understood it right, there
might be two possibilities of building roughly about 250 sq ft and/or
750 sq ft on this land.
--------------------------------------------------------------------------------------
----------------------------------------------------------
9
--------------------------------------------------------------------------------------
----------------------------------------------------------
10
--------------------------------------------------------------------------------------
----------------------------------------------------------
11
If these numbers was about right, do you think I would be a good
candidate to apply for a variance and get approved?
If the answer was a probably no, I wont waste my time and energy
and yours and instead, I would focus on paying for land in full as
soon as I can and finding the most reasonable scenarios for me to
build on it.
So, I appreciate some hint or feedback in this regard in the meeting
tomorrow. Effective communication matters.
Please provide me with the steps that I should take
to build on this land.
Please provide me with the relevant keywords and
key ideas. Please don't assume that I know,
because I probably don't know.
What should I do very first? Then what should I do?
Then when should I do? Then what should I do?
Then what should I do? Until I complete building on
this land while I am in compliance with the City.
I go find the more details and costs of each steps.
12
I have talked to a few concrete and asphalt paving companies.
I have talked to a few engineering companies in regard to surveying
and planning.
I have talked to a few tiny home builders regarding putting a tiny
home on the land. The last word from the city was a building permit
is required in any cases and it must be built or located on a
foundation. Is that correct? Is there any way around it? Any tweak
that can lower the costs? Any scenario of building that does not
need foundation? and/or does not need building permit?
Please help me think and act procedural and
provide me with the steps
13
The following are the scenarios I consider in case of unreasonably
and unaffordably high cost of building a commercial on the land.
Would City let me put a shed like this on the land and use it as a
residence or temporary residence?
I have a short video clip of something similar with only a few
thousand dollar cost.
14
Would city let me put a trailer like this on the land and use it as a
residence or temporary residence?
15
Could this setup be a possibility for the land at 448 Addison Ave
16
17
Looking forward to seeing you tomorrow and get your valuable
information, guidance, and advise at 02:00 PM
Objectives of the Meeting:
1) Is there any costly problem or restriction or obligation that city
didn't tell me yet about in regard to this land that I should be
aware of before buying the land? I am planning to buy this land in a
few days.
2) In summary, Should I apply for a variance? If it is probably a no, I
wouldn't apply. Instead, I look into what cost-wise correct things can
be done while meeting the city requirement instead.
18
3) The Steps to build from beginning to the end. (Something like a
flowchart that I can picture the whole thing with the timing and
costs before I step into it)
4) The acceptability or not-acceptability of alternative or temporary
building to use the land as a residence.
Sincerely, Behn
On Tue, Jun 11, 2024 at 11:26 AM Kelly Wright <kwright@tfid.org> wrote:
To build with variance or without. Ben wants to know what would be the steps to build on this
land. From A to Z. With or without applying for a variance. Ben has done some measurements and
has two sizes for the possible building. One with residential and one with commercial. His concern is
to get the job done at the lowest possible cost. To stay in compliance with all city requirements. He is
in the process of inspecting the land before he buys. He wants to make sure there is no additional
standards. Ben wants to make sure there are no obligations that have not been discussed.
19