HomeMy WebLinkAboutInterview Notes_TF Animal Shelter S�trr Twin Fall Animal Shelter Expansion CM/GC Interviews October 22, 2025 *Items to look for: • Are they someone you could work with on this project? • Does their team communicate well amongst themselves and with us? • Did they bring their project manager and/or superintendent?These are the people we will have the most day-to-day contact with our team. • Do they have an obvious leader who is capable of communicating on behalf of the contractors and the Council, patrons, and media? • Are they client oriented or contractor oriented? • Do they have local knowledge and connections? 1. As the CM/GC of this project you will develop and maintain the project construction schedule.. How do you manage a phased project and can there be any cost savings in doing so? Cott --- 2. What is the biggest challenge the City will face in delivering this project and what can you do to help overcome that challenge? 3. Provide an example of a project where you have had to perform construction operations in an occupied facility. What strategies did you use to be successful and ensure occupants can still perform their job duties? , / 4. How do you communicate challenges, change orders/revisions, delays, etc to the owner? - �0 5. Will you provide us with a detailed list of general project conditions and requirements, including fee inclusions/exclusions?Are you willing to negotiate fee structure of the general conditions and requirements? 6. Are you willing to work with subcontractors t at want to make in-kind donations? 7. Other: Twin Fall Animal Shelter Expansion CM/GC Interviews October 22, 2025 *Items to look for: • Are they someone you could work with on this project? • Does their team communicate well amongst themselves and with us? • Did they bring their project manager and/or superintendent?These are the people we will have the most day-to-day contact with our team. • Do they have an obvious leader who is capable of communicating on behalf of the contractors and the Council, patrons, and media? • Are they client oriented or contractor oriented? • Do they have local knowledge and connections? 1. As the CM/GC of this project you will develop and maintain the project construction schedule. How do you manage a phased project and can there be any cost savings in doing so? 2. What is the biggest challenge the City will face in delivering this project and what can you do to help overcome that challenge? 't's. '04- kLASZ'&(_ r.,t4r-4 a-,- n_ai V�LU 67X s r 3. Provide an example of a project where you have had to perform construction operations in an occupied facility. What strategies did you use to be successful and ensure occupants can still perform their job duties? I)T evie/nek 01 sf, O't5 A„Ldf 4. How do you communicate challenges, change orders/revisions, delays, etc to the owner? 5. Will you provide us with a detailed list of general project conditions and requirements, including fee inclusions/exclusions?Are you willing to negotiate fee structure of the general conditions and requirements? 'r -_ 6. Are you willing to work with subcontractors that want to make in-kind donations? A-F 1,4,, i.w �t oL F �'5; ira,1��u k2ri 7. Other: Twin Fall Animal Shelter Expansion CM/GC Interviews October 22, 2025 *Items to look for: • Are they someone you could work with on this project? • Does their team communicate well amongst themselves and with us? • Did they bring their project manager and/or superintendent?These are the people we will have the most day-to-day contact with our team. • Do they have an obvious leader who is capable of communicating on behalf of the contractors and the Council, patrons, and media? • Are they client oriented or contractor oriented? • Do they have local knowledge and connections? 1. As the CM/GC of this project you will develop and maintain the project construction schedule. How do you manage a phased project and can there be any cost savings in doing so? 2. What is the biggest challenge the City will face in delivering this project and what n you do to help overcome that challenge? P 3. Provide an example of a project where you have had to perform construction operations in an occupied facility. What strategies did you use to be successful and ensure occupants can r still perform their job duties? J i 4. How do you communicate challenges, change orders/revisions, delays, etc to the owner? 5. Will you provide us with a detailed list of general project conditions and requirements, including fee inclusions/exclusions?Are you willing to negotiate fee structure of the general conditions and requirements? 6. Are you willing to work with subcontractors that want to make in-kind donations? 7, Other: sizk-Irv- Twin Fall Animal Shelter Expansion CM/GC Interviews October 22, 2025 *Items to look for: • Are they someone you could work with on this project? • Does their team communicate well amongst themselves and with us? • Did they bring their project manager and/or superintendent?These are the people we will have the most day-to-day contact with our team. • Do they have an obvious leader who is capable of communicating on behalf of the contractors and the Council, patrons, and media? • Are they client oriented or contractor oriented? • Do they have local knowledge and connections? 1. As the CM/GC of this project you will develop and maintain the project construction schedule. How do[you manage a phased project and can there be any cost savings in doing so? 0 plolec grkci 26tq, /h r�2 What is the biggest challenge the City will face in delivering this project and what can you I4, to help overcome that challenge? / /"fig,rGa/_' M4 6" Cj le"1livG, 3. Provide an example of a project where you have had to perform construction operations in an occupied facility. What strategies did you use to be successful and ensure occupants can still perform their job duties? 6P/,trlGG JdrA % chi f� _r"I �4 How //do you communicate challenges, change orders/revisions, delays, etc to the owner? Ay 5. Will you provide us with a detailed list of general project conditions and requirements, including fee inclusions/exclusions?Are you willing to negotiate fee structure of the general conditions and requirements? 7.7-- 6, Are you willing to work with subcontractors that want to make in-kind donations? Yeir — ,�t i;.<� in �;J P,c/'al e. t 7. Other: s u,h",jr- Twin Fall Animal Shelter Expansion CM/GC Interviews October 22, 2025 *Items to look for: • Are they someone you could work with on this project? • Does their team communicate well amongst themselves and with us? • Did they bring their project manager and/or superintendent?These are the people we will have the most day-to-day contact with our team. • Do they have an obvious leader who is capable of communicating on behalf of the contractors and the Council, patrons, and media? • Are they client oriented or contractor oriented? • Do they have local knowledge and connections? 1. As the CM/GC of this project you will develop and maintain the project construction schedule. How do you manage a phased project and can there be any cost savings in doing so? 2. What is the biggest challenge the City will face in delivering this project and wha an u do to help overcome that challenge? 00 rjot- ckQl(e 3. Provide an example of a project where you have had to perform construction operations in an occupied facility. What strategies did you use to be successful and ensure occupants can still perform their job duties? 4. How do you communicate challenges, change orders/revisions, delays, etc to the owner? iAJ �- 5. Will you provide us with a detailed list of general project conditions and requirements, including fee inclusions/exclusions?Are you willing to negotiate fee structure of the general conditions and requirements? 6. Are you willing to work with subcontractors that want to make in-kind donations? 7. Other: Twin Fall Animal Shelter Expansion CM/GC Interviews October 22, 2025 *Items to look for: • Are they someone you could work with on this project? • Does their team communicate well amongst themselves and with us? • Did they bring their project manager and/or superintendent?These are the people we will have the most day-to-day contact with our team. • Do they have an obvious leader who is capable of communicating on behalf of the contractors and the Council, patrons, and media?• Are they client oriented or contractor oriented? • Do they have local knowledge and connections? PN� 1. As the CM/GC of this project you will develop and maintain the project construction schedule. How do you manage a phased project and can there be any cost savings in doing so? 2. What is the biggest challenge the City will face in delivering this project and what can you do to help overcome that challenge? 4-n V-1 3. Provide an example of a project where you have had to perform construction operations in an occupied facility. What strategies did you use to be successful and ensure occupants can still perform their job duties? G CXMVr1.ww,C_ - 9-11-- C."" t 4. How do you communicate challenges, change orders/revisions, delays, etc to the owner? Urge J 5. Will you provide us with a detailed list of general project conditions and requirements, including fee inclusions/exclusions?Are you willing to negotiate fee structure of the general conditions and requirements? 6. Are you willing to work with subcontractors that want to make in-kind donations? ai '� J&V$ - 7. Other: Twin Fall Animal Shelter Expansion CM/GC Interviews October 22, 2025 *Items to look for: • Are they someone you could work with on this project? • Does their team communicate well amongst themselves and with us? • Did they bring their project manager and/or superintendent?These are the people we will have the most day-to-day contact with our team. • Do they have an obvious leader who is capable of communicating on behalf of the contractors and the Council, patrons, and media? • Are they client oriented or contractor oriented? • Do they have local knowledge and connections? 1. As the CM/GC of this project you will develop and maintain the project construction schedule. How do you manage a phased project and can there be any cost savings in doing so? Q CY CV/VW P 2. What is the biggest challenge the City will face in delivering this project and what can you do to help overcome that challenge? O 3. Provide an example of a project where you have had to perform construction operations in an occupied facility. What strategies did you use to be successful and ensure occupants can still perform their job duties? O 4. How do you communicate challenges, change orders/revisions, delays, etc to the owner? 5. Will you provide us with a detailed list of general project conditions and requirements, including fee inclusions/exclusions?Are you willing to negotiate fee structure of the general conditions and requirements? 6. Are you willing to work with subcontractors that want to make in-kind donations? 7. Other: 5ubwV-hA�n Twin Fall Animal Shelter Expansion CM/GC Interviews October 22, 2025 *Items to look for: • Are they someone you could work with on this project? • Does their team communicate well amongst themselves and with us? • Did they bring their project manager and/or superintendent?These are the people we will have the most day-to-day contact with our team. • Do they have an obvious leader who is capable of communicating on behalf of the contractors and the Council, patrons, and media? • Are they client oriented or contractor oriented? • Do they have local knowledge and connections? 1. As the CM/GC of this project you will develop and maintain the project construction schedule. How do you manage a phased project and can there be any cost savings in doing so? % YES Lw -' drr— /lUy►it/ 04yi' ho 4/prv,i G 11,ri Flo p G(IfloMee- AIX i e, of c �e9 rya, 2 What is the biggest challenge the City will face in delivering this project and what can you do to help overcome that challenge? AC41t eIlhej t 1;1y (, /p AA��iJJ�+�! f R ® C�Af ✓Go r� /71�V 3. Provide an example of a project where you have had to perform construction operations in an occupied facility. What strategies did you use to be successful and ensure occupants can still perform their job duties? /y,0// i i �4 How do you communicate challenges, change orders/revisions, delays, etc to the owner? w'olve (Y"le !-Mar,lr� r d.A C. GJte�(y /jj " Cll fie, AbVA/4, �W&elc 4,o k 4 e. 5. Will you provide us with a detailed list of general project conditions and requirements, including fee inclusions/exclusions?Are you willing to negotiate fee structure of the general conditions and requirements? ej- — )eA.1et 6i_rI. .Lrr�vl�/tC� �di/T i u4 omre//l e . 6. Are you willing to work.with subcontractors that want to make in-kind donations? ,I -- i� c Awk , n 1cr-,,1 yes ;/ ,,/- 7. other: Twin Fall Animal Shelter Expansion CM/GC Interviews October 22, 2025 *Items to look for: • Are they someone you could work with on this project? • Does their team communicate well amongst themselves and with us? • Did they bring their project manager and/or superintendent?These are the people we will have the most day-to-day contact with our team. • Do they have an obvious leader who is capable of communicating on behalf of the contractors and the Council, patrons, and media? • Are they client oriented or contractor oriented? • Do they have local knowledge and connections? 1. As the CM/GC of this project you will develop and maintain the project construction schedule. How do you manage a phased project and can there be any cost savings in doing so? ,�t,,dt, ��"f wt,.D� � I'►�c.�r"�-�t�e. �'"�+r►-u-l�t..r..�..1 2. What is the biggest challenge the City will face in delivering this project and what can you do to help overcome that challenge? T q t yt'A LC!WL-i2Q., yvLA vk-i wL,;V vL3XS oru -h iaV.- 3. Provide an example of a project where you have had to perform construction operations in an occupied facility. What strategies did you use to be successful and ensure occupants can still perform their job duties? 411(W 4. How do you communicate challenges, change orders/revisions, delays, etc to the owner? 5. Will you provide us with a detailed list of general project conditions and requirements, including fee inclusions/exclusions?Are you willing to negotiate fee structure of the general conditions and requirements? y, 6. Are you willing to work with subcontractors that want to make in-kind donations? VW�T 7. Other: i Twin Fall Animal Shelter Expansion CM/GC Interviews October 22, 2025 *Items to look for: • Are they someone you could work with on this project? • Does their team communicate well amongst themselves and with us? • Did they bring their project manager and/or superintendent? These are the people we will have the most day-to-day contact with our team. • Do they have an obvious leader who is capable of communicating on behalf of the contractors and the Council, patrons, and media? • Are they client oriented or contractor oriented? • Do they have local knowledge and connections? Jet��Zec�. S 1. As the CM/GC of this project you will develop and maintain the project construction schedule. How do you manage a phased project and can there be any cost savings in doing so? 14 .1 A (q I &a 5 tw 2. What is the biggest challenge the City will face in delivering this project and what can you do to help overcome that challenge? Provide an example of a project where you have had to perform construction operations in an occupied facility. What strategies did you use to be successful and ensure occupants can still perform their job duties? i i I I i 4. How do you communicate challenges, change orders/revisions, delays, etc to the owner? 5. Will you provide us with a detailed list of general project conditions and requirements, including fee inclusions/exclusions?Are you willing to negotiate fee structure of the general conditions and requirements? 6. Are you willing to work with subcontractors that want to make in-kind donations? 7. Other: Twin Fall Animal Shelter Expansion CM/GC Interviews October 22, 2025 *Items to look for: • Are they someone you could work with on this project? • Does their team communicate well amongst themselves and with us? • Did they bring their project manager and/or superintendent?These are the people we will have the most day-to-day contact with our team. • Do they have an obvious leader who is capable of communicating on behalf of the contractors and the Council, patrons, and media? • Are they client oriented or contractor oriented? • Do they have local knowledge and connections? 1. As the CM/GC of this project you will develop and maintain the project construction schedule. Wow do you manage a phased project and can there be any cost savings in doing so? 2� What is the biggest challenge the City will face in delivering this project and what can you do to help overcome that challenge? ��ecc✓�; 3. Provide an example of a project where you have had to perform construction operations in an occupied facility. What strategies did you use to be successful and ensure occupants can still ��perform pqtheir job duties? How do you communicate challenges, change orders/revisions, delays, etc to the owner? IfCY 0/1 We e IVY 5, Will you provide us with a detailed fist of general project conditions and requirements, including fee inclusions/exclusi9ns?Are you willing to negotiate fee structure of the general conditions and requirements? 9-0o/ y Ve kxell'yl b4kl y �grsed d,,' /.0 6. Are you willing to work with subcontractors that want to make in-kind donations? Are b A y 1x'A,*xet- hr/W jz'�) - l4yf1ib 7. Other: m 1 Twin Fall Animal Shelter Expansion CM/GC Interviews October 22, 2025 *Items to look for: • Are they someone you could work with on this project? • Does their team communicate well amongst themselves and with us? • Did they bring their project manager and/or superintendent?These are the people we will have the most day-to-day contact with our team. • Do they have an obvious leader who is capable of communicating on behalf of the contractors and the Council, patrons, and media? • Are they client oriented or contractor oriented? • Do they have local knowledge and connections? 1. As the CM/GC of this project you will develop and maintain the project construction schedule. How do you manage a phased project and can there be any cost savings in doing Ka"�' , Q�w ' VAAOR., 2. What is the biggest challenge the City will face in delivering this project and what can you do to help overcome that challenge? r 3. Provide an example of a project where you have had to perform construction operations in an occupied facility. What strategies did you use to be successful and ensure occupants can still perform their job duties? 4. How do you communicate challenges, change orders/revisions, delays, etc to the owner? pcz� 5. Will you provide us with a detailed list of general project conditions and requirements, including fee inclusions/exclusions?Are you willing to negotiate fee structure of the general conditions and requirements? 6. Are you willing to work with subcontractors that want to make in-kind donations? 7. Other: R 3(�✓ Twin Fall Animal Shelter Expansion CM/GC Interviews October 22, 2025 *Items to look for: • Are they someone you could work with on this project? • Does their team communicate well amongst themselves and with us? • Did they bring their project manager and/or superintendent?These are the people we will have the most day-to-day contact with our team. • Do they have an obvious leader who is capable of communicating on behalf of the contractors and the Council, patrons, and media? • Are they client oriented or contractor oriented? • Do they have local knowledge and connections? 1. As the CM/GC of this project you will develop and maintain the project construction schedule. How do you manage a phased project and can there be any cost savings in doing so? �. hdi ra f 1P-4(-sal►" re — 2. What is the biggest challenge the City will face in delivering this project and what can you do to help overcome that challenge? 3. Provide an example of a project where you have had to perform construction operations in an occupied facility. What strategies did you use to be successful and ensure occupants can still perform their job duties? C.44t4 b Cs w lnti U o CVL G -` 4. Now do you communicate challenges, change orders/revisions, delays, etc to the owner? � P"CdV_e__ q�yc. L to 5. Will you provide us with a detailed list of general project conditions and requirements, including fee inclusions/exclusions?Are you willing to negotiate fee structure of the general conditions and requirements? V 6, Are you willing to work with subcontractors that want to make in-kind donations? 7, Other; S�VlN'�� j S�l•�-�S P` ,— Twin Fall Animal Shelter Expansion CM/GC Interviews October 22, 2025 *Items to look for: • Are they someone you could work with on this project? • Does their team communicate well amongst themselves and with us? • Did they bring their project manager and/or superintendent? These are the people we will have the most day-to-day contact with our team. • Do they have an obvious leader who is capable of communicating on behalf of the contractors and the Council, patrons, and media? • Are they client oriented or contractor oriented? • Do they have local knowledge and connections? 1. As the CM/GC of this project you will develop and maintain the project construction schedule. How do you manage a phased project and can there be any cost savings in doing so? D 2. What is the biggest challenge the City will face in delivering this project and what can you do to help overcome that challenge? 3. Provide an example of a project where you have had to perform construction operations in an occupied facility. What strategies did you use to be successful and ensure occupants can still perform their job duties? a 4. How do you communicate challenges, change orders/revisions, delays, etc to the owner? 5. Will you provide us with a detailed list of general project conditions and requirements, including fee inclusions/exclusions? Are you willing to negotiate fee structure of the general conditions and requirements? 6. Are you willing to work with subcontractors that want to make in-kind donations? UL P 7. Other: ark /1 Vv _ P gc' Twin Fall Animal Shelter Expansion CM/GC Interviews October 22, 2025 *Items to look for: • Are they someone you could work with on this project? • Does their team communicate well amongst themselves and with us? • Did they bring their project manager and/or superintendent?These are the people we will have the most day-to-day contact with our team. • Do they have an obvious leader who is capable of communicating on behalf of the contractors and the Council, patrons, and media? • Are they client oriented or contractor oriented? • Do they have local knowledge and connections? 1. As the CM/GC of this project you will develop and maintain the project construction schedule. How do you manage a phased project and can there be any cost savings in doing so? bCA G��6ew _44A k fAA02- 2. What is the biggest challenge the City will face in delivering this project and what can you do to help overcome that challenge? ^ 3. Provide an example of a project where you have had to perform construction operations in an occupied facility. What strategies did you use to be successful and ensure occupants can y still perform their job duties? 4. How do you communicate challenges, change orders/revisions, delays, etc to the owner? 5. Will you provide us with a detailed list of general project conditions and requirements, including fee inclusions/exclusions?Are you willing to negotiate fee structure of the general conditions and requirements? des 6. Are you willing to work with subcontractors that want to make in-kind donations? 7. Other: PAL Twin Fall Animal Shelter Expansion CM/GC Interviews October 22, 2025 *Items to look for: • Are they someone you could work with on this project? • Does their team communicate well amongst themselves and with us? • Did they bring their project manager and/or superintendent?These are the people we will have the most day-to-day contact with our team. • Do they have an obvious leader who is capable of communicating on behalf of the contractors and the Council, patrons, and media? • Are they client oriented or contractor oriented? • Do they have local knowledge and connections? 1. As the CM/GC of this project you will develop and maintain the project construction schedule. How do you manage a phased project and can there be any cost savings in doing so?L0��, dke t# �2 What is the biggest challenge the City will face in delivering this project and what can you do to help overcome that challenge? 3. Provide an example of a project where you have had to perform construction operations in an occupied facility. What strategies did you use to be successful and ensure occupants can still perform their job duties? fB�e/l W%f�h� 4� ow do you communicate challenges, change orders/revisions, delays, etc to the owner? PdG✓IIE(I1 lw�//l Ame C-11r, dim - C�.ia , C'm�.►�tr G�+�f� Al lee l- wei kly, V��/Ct/ �!l�lbQl /I�lr 5. Will you provide us with a detailed list of general project conditions and requirements, including fee inclusions/exclusions?Are you willing to negotiate fee structure of the general conditions and requirements? V�S! 6. Are you willing to work with subcontractors that want to make in-kind donations? 7-,41fr— MV;c Fes1 1cs, �r.6lr,•, - o � '�1 wr.�. 7. Other: ) J r, n P.or ly e�+ rJi A Z�2�, Twin Fall Animal Shelter Expansion - CM/GC Interviews October 22, 2025 *Items to look for: • Are they someone you could work with on this project? • Does their team communicate well amongst themselves and with us? • Did they bring their project manager and/or superintendent?These are the people we will have the most day-to-day contact with our team. • Do they have an obvious leader who is capable of communicating on behalf of the contractors and the Council, patrons, and media? • Are they client oriented or contractor oriented? • Do they have local knowledge and connections? 1. As the CM/GC of this project you will develop and maintain the project construction schedule. How do you manage a phased project and can there be any cost savings in doing so? 2. What is the biggest challenge the City will face in delivering this project and what can you do to help overcome that challenge? 3. Provide an example of a project where you have had to perform construction operations in an occupied facility. What strategies did you use to be successful and ensure occupants can still perform their job duties? r � 4UAMq,- o v i 4. How do you communicate challenges, change orders/revisions, delays, etc to the owner? 5. Will you provide us with a detailed list of general project conditions and requirements, including fee inclusions/exclusions?Are you willing to negotiate fee structure of the general conditions and requirements? 6. Are you willing to work with subcontractors that want to make in-kind donations? 7, Other: CC FLE Twin Fall Animal Shelter Expansion CM/GC Interviews October 22, 2025 *Items to look for: • Are they someone you could work with on this project? • Does their team communicate well amongst themselves and with us? • Did they bring their project manager and/or superintendent?These are the people we will have the most day-to-day contact with our team. • Do they have an obvious leader who is capable of communicating on behalf of the contractors and the Council, patrons, and media? • Are they client oriented or contractor oriented? • Do they have local knowledge and connections? 1. As the CM/GC of this project you will develop and maintain the project construction schedule. How do you manage a phased project and can there be any cost savings in doing so? 2. What is the biggest challenge the City will face in delivering this project and what can you do to help overcome t at challenge? 3. Provide an example of a project where you have had to perform construction operations in an occupied facility. What strategies did you use to be successful and ensure occupants can still perform their job duties? 4. How do you communicate challenges, change orders/revisions, delays, etc to the owner? �C61-e 5. Will you provide us with a detailed list of general project conditions and requirements, including fee inclusions/exclusions?Are you willing to negotiate fee structure of the general conditions and requirements? 6. Are you willing to work with subcontractors that want to make in-kind donations? 7. Other: Q Cow. Twin Fall Animal Shelter Expansion CM/GC Interviews October 22, 2025 *Items to look for: • Are they someone you could work with on-this project? • Does their team communicate well amongst themselves and with us? • Did they bring their project manager and/or superintendent?These are the people we will have the most day-to-day contact with our team. • Do they have an obvious leader who is capable of communicating on behalf of the contractors and the Council, patrons, and media? • Are they client oriented or contractor oriented? • Do they have local knowledge and connections? 1. As the CM/GC of this project you will develop and maintain the project construction schedule. How do you manage a phased project and can there be any cost savings in doing Afee Axrlf - A 1 4 -f--t 6 AJj ItAyof4-fcs - 5-C-61'f .�- wa/I4 2 What is the biggest challenge the City will face in delivering this project and what can you duo to help overcome that challenge? Wen At ve l qv6 a.4 J 3. Provide an example of a project where you have had to perform construction operations in an occupied facility. What strategies did you use to be successful and ensure occupants can still perform their job duties? ZAt 6f 4J , ,fie;r r,l flee./A� i V How do you communicate challenges, change orders/revisions, delays, etc to the owner? fe Am 0 5. Will you provide us with a detailed list of general project conditions and requirements, including fee inclusions/exclusions?Are you willing to negotiate fee structure of the general conditions and requirements?1¢f r 6. A�r!e you willing to work with subcontractors that want to make in-kind donations? ��rPl/i do Ge a�'i ��?r lei► 7. Other: Twin Fall Animal Shelter Expansion CM/GC Interviews October 22, 2025 *Items to look for: • Are they someone you could work with on this project? • Does their team communicate well amongst themselves and with us? • Did they bring their project manager and/or superintendent?These are the people we will have the most day-to-day contact with our team. • Do they have an obvious leader who is capable of communicating on behalf of the contractors and the Council, patrons, and media? • Are they client oriented or contractor oriented? • Do they have local knowledge and connections? 1. As the CM/GC of this project you will develop and maintain the project construction schedule. Mow do you manage a phased project and can there be any cost savings in doing so? 11," , P s c/t'� r� 2. What is the biggest challenge the City will face in delivering this project and what can you do to help overcome that challenge? ash V,.(, 4a U ' 3. Provide an example of a project where you have had to perform construction operations in an occupied facility. What strategies did you use to be successful and ensure occupants can still perform their job duties? IZbd 4- v -�rAj&c c,,.•�-�- �(�`�✓�-fir °-�. r i 4. How do you communicate challenges, change orders/revisions, delays, etc to the owner? 5. Will you provide us with a detailed list of general project conditions and requirements, including fee inclusions/exclusions?Are you willing to negotiate fee structure of the general conditions and requirements? 6. Are you willing to work with subcontractors that want to make in-kind donations? �YL V4 n'k 7. Other: R+f Twin Fall Animal Shelter Expansion CM/GC Interviews October 22, 2025 *Items to look for: • Are they someone you could work with on this project? • Does their team communicate well amongst themselves and with us? • Did they bring their project manager and/or superintendent?These are the people we will have the most day-to-day contact with our team. • Do they have an obvious leader who is capable of communicating on behalf of the contractors and the Council, patrons, and media? •_ Are they client oriented or contractor oriented? • Do they have local knowledge and connections? 1. As the CM/GC of this project you will develop and maintain the project construction schedule. How do you manage a phased project and can there be any cost savings in doing so? FkA/�i A RX - p 2. What is the biggest challenge the City will face in delivering this project and what can you do to help overcome that challenge? 3. Provide an example of a project where you have had to perform construction operations in an occupied facility. What strategies did you use to be successful and ensure occupants can still perform their job duties? 4. How do you communicate challenges, change orders/revisions, delays, etc to the owner? 5. Will you provide us with a detailed list of general project conditions and requirements, including fee,inclusions/exclusions?Are you willing to negotiate fee structure of the general conditions and requirements? 6. Are you willing to work with subcontractors that want to make in-kind donations? my 7. Other: 4- Aw wW S+74, ��'� �"2. rrrv,SS i f i f `s Twin Fall Animal Shelter Expansion CM/GC Interviews \ October 22, 2025 1 *Items to look for: • Are they someone you could work with on this project? • Does their team communicate well amongst themselves and with us? • Did they bring their project manager and/or superintendent?These are the people we will have the most day-to-day contact with our team. • Do they have an obvious leader who is capable of communicating on behalf of tie contractors and the Council, patrons, and media? -' Y • Are they client oriented or contractor oriented? P • Do they have local knowledge and connections? 1. As the CM/GC of this project you will develop and maintain the project construction schedule. How do you manage a phased project and can there be any cost savings in doing so? (t� 2. What is the biggest challenge the City will face in delivering this project and what can you do to help overcome that challenge? 05 -- 3. Provide an example of a project where you have had to perform construction operations in an occupied facility. What strategies did you use to be successful and ensure occupants can still perform their job duties? 04 pc aw ��✓ � , 5 I 4. How do you communicate challenges, change orders/revisions, delays, etc to the owner? 5. Will you provide us with a detailed list of general project conditions and requirements, including fee inclusions/exclusions?Are you willing to negotiate fee structure of the general conditions and requirements? 6. Are you willing to work with subcontractors that want to make in-kind donations? 7. Other: Twin Fall Animal Shelter Expansion CM/GC Interviews October 22, 2025 *Items to look for: • Are they someone you could work with on this project? • Does their team communicate well amongst themselves and with us? • Did they bring their project manager and/or superintendent?These are the people we will have the most day-to-day contact with our team.K • Do they have an obvious leader who is capable of communicating on behalf of the contractors and the Council, patrons, and media? • Are they client oriented or contractor oriented? • Do they have local knowledge and connections?ycf 1. As the CM GC of this project you will develop and maintain the project construction schedule. How do you manage a phased project and can there be any cost savings in doing CAI 'WJ/1 What is the biggest challenge the City will face in delivering this project and what can you do to help overcome that challenge? JA III -A 3. Provide an example of a project where you have had to perform construction operations in an occupied facility. What strategies did you use to be successful and ensure occupants can stti/ill perform their job duties? G drd/din 7/t s 4. How do you communicate challenges, change orders/revisions, delays, etc to the owner? D�tn C®mM•�niG�,j�:sn OPI ��FE�• �ro Z lc C�¢y /�lclsf 5. Will you provide us with a detailed list of general project conditions and requirements, including fee inclusions/exclusions?Are you willing to negotiate fee structure of the general conditions and requirements? xeplr.A �{o cr1/Y Ra/c, / 6. Are•y�goulwilllling to work with subcontractors that want to make in-kind donations? rPI 7. Other: �ojP�c it j��,j! f�'.✓�,rd Pwk 1j'a A/ oe-wkra N v o-o/ Y �� f Twin Fall Animal Shelter Expansion CM/GC Interviews October 22, 2025 *Items to look for: • Are they someone you could work with on this project? • Does their team communicate well amongst themselves and with us? • Did they bring their project manager and/or superintendent?These are the people we will have the most day-to-day contact with our team. • Do they have an obvious leader who is capable of communicating on behalf of the contractors and the Council, patrons, and media? • Are they client oriented or contractor oriented? • Do they have local knowledge and connections? 1. As the CM/GC of this project you will develop and maintain the project construction schedule. How do you manage a phased project and can there be any cost savings in doing so? �'J Q5 2. What is the biggest challenge the City will face in delivering this project and what can you do to help overcome that challenge? - C 3. Provide an example of a project where you have had to perform construction operations in an occupied facility. What strategies did you use to be successful and ensure occupants can still perform their job duties? 4. How do you communicate challenges, change orders/revisions, delays, etc to the owner? 5. Will you provide us with a detailed list of general project conditions and requirements, including fee inclusions/exclusions?Are you willing to negotiate fee structure of the general conditions and requirements? 6. Are you willing to work with subcontractors that want to make in-kind donations? 4n � r , A 7. Other: